The electrical date on a renovation is not really ours, it is your drywall date. Rough-in has to be inspected while everything is still visible, so that one date drives the whole sequence.
Sequence
Cables get run and boxes get set while the framing is open. That work is then inspected before anything covers it, and only after that do the walls close. Booking the electrical late is the single most common way a trade delays a build, because the inspection cannot be skipped or done afterwards, and permits and certificates explains why.
So the useful thing to tell us on the first call is the drywall date. Everything else arranges itself around it, and where the date moves we would rather know than discover.
It is also the moment when everything else is cheapest. Adding a circuit, moving a position or running a feed for something you are planning costs a fraction now, which is why pot light installation and outlet and switch installation both belong in this window rather than after.
How it runs
It drives the whole sequence, because rough-in has to be inspected while everything is still visible.
Positions decided against furniture and use rather than against the drawing. Cheap now, expensive later.
Cables run, boxes set, then presented for inspection before anything is covered.
Devices and fittings once the finishes are in, then the certificate to you.
Basements and suites
A basement conversion is not one circuit, it is several: lighting, general outlets, whatever the room is for, and often a bathroom or a kitchenette with their own protection requirements. That group is usually better landed in one place, which is what a subpanel does.
The other thing basements bring is old wiring. Existing circuits running through the space are frequently the oldest in the house, and new work cannot be extended from knob and tube.
Where the finished circuit count exceeds what the service can carry, an electrical panel upgrade becomes part of the project rather than a discovery, and doing it during the renovation is cheaper than doing it afterwards.
Related work
Common questions
Booked rough-in against our drywall date without being chased about it once.
Walked the plan with us and moved three positions before anything was run.
Found knob and tube in the basement at framing stage rather than at second fix.
Did the panel work during the build. Would have cost far more as a separate job.